Construction Agreements in Return for Land Share (also known as land-share construction contracts) are hybrid contracts under Turkish civil law. They combine the characteristics of an construction contract (obligation to construct a building) and a promise to sell real estate (obligation to transfer land titles). When a contractor fails to complete the construction, deviates from the project layout, or abandons the work, landowners often seek to terminate the contract. However, terminating these official contracts involves strict, complex legal parameters.

1. Can a Construction Agreement Be Terminated Unilaterally in Turkey?

Under Turkish law, because these contracts involve property title transfers, they must be drafted officially by a notary. Therefore, neither party can terminate the agreement unilaterally through a simple declaration or notification. Valid termination requires one of the following methods:

  • Mutual Consent (Termination Protocol): The parties must sign a mutual termination agreement in official notary format.
  • Judicial Dissolution (Court Lawsuit): If mutual agreement is not possible, the party seeking dissolution must file a lawsuit in the Civil Court of First Instance to obtain a court decree of termination.

2. Retroactive (Ex Tunc) vs. Prospective (Ex Nunc) Termination

The legal consequences of a termination lawsuit depend heavily on the physical completion rate of the building at the time of the dispute:

  • Retroactive Termination: If the completion rate is low (typically under 90%), the court rules for retroactive termination. The contract is treated as if it never existed, titles are returned to the landowner, and the contractor can only claim the value of materials under unjust enrichment principles.
  • Prospective Termination: If the completion rate is 90% or higher, the principle of good faith (Article 2 of the Turkish Civil Code) prevents retroactive cancellation. The court rules for prospective termination, granting the contractor units proportional to their completed work, while the landowner can claim damages for unfinished and defective works.

3. Rights of the Landowner in Case of Contractor's Default

If the contractor fails to deliver the property within the agreed duration, the landowner can exercise several statutory options:

  • Demand specific performance (completion of the building) and claim delay compensation (loss of rent) for the duration of the delay.
  • Seek court permission for performance on behalf of the contractor (nama ifaya izin), allowing the landowner to complete the construction and charge all costs to the contractor.
  • Terminate the agreement due to default and sue for damages (either positive or negative damages depending on the nature of the termination).

4. Title Risks for Third-Party Buyers

Contractors frequently sell their designated units to third-party buyers during the construction phase. However, if the contractor defaults and the agreement is retroactively terminated, the tapu (title deed) transfers to third parties are cancelled, and the properties revert to the landowner. The Turkish Supreme Court rules that third parties cannot claim good faith protection (TMK Art. 1023), as they should anticipate that the contractor's title is dependent on the completion of the construction.

Frequently Asked Questions

For detailed information and legal consultation, you can visit our Zoning Law and Real Estate Law pages, or request an appointment via our Contact page.

What is 'Performance on Behalf of the Contractor' (Nama İfaya İzin)?

It is a court authorization allowing the landowner to complete the unfinished construction of the defaulted contractor, paying for it using the contractor's assets or claiming the expenses from them directly.

What is the statute of limitations for construction contract disputes?

The general statute of limitations for contract disputes is 5 years from the delivery date or the date of default. If there is gross negligence or intentional fault, the period is extended to 20 years.

Can I claim both a penalty clause and loss of rent at the same time?

Unless agreed otherwise in the contract, a penal clause for delay and actual rent loss can generally be claimed together. However, this depends on whether the penal clause is defined as cumulative or alternative.

1. Court of Cassation General Assembly Precedent Decision: Validity Condition of Land-for-Flat Agreements

Court of Cassation, General Assembly of Civil Chambers – File: 2023/574, Decision: 2024/319

Summary: Land-for-flat construction agreements that include the transfer of ownership of real property must be executed before a notary public in order to be valid. Agreements concluded outside of the official form are absolutely null and void and cannot be enforced.

"...Hukuk Dairesinin 12.05.2022 tarihli ve 2022/1536 Esas, 2022/2678 Karar sayılı BOZMA kararı..."
View Full Decision (Turkish)

2. Court of Cassation General Assembly Precedent Decision: Contractor's Delay and Termination Rights

Court of Cassation, General Assembly of Civil Chambers – File: 2024/170, Decision: 2025/47

Summary: Where a contractor fails to deliver the construction on time and falls into delay, the landowner has the right to terminate the agreement and claim compensation. However, the compensation must be calculated based on the concrete damage suffered, not the total project value.

"...Hukuk Dairesinin 07.10.2021 tarihli ve 2021/987 Esas, 2021/706 Karar sayılı BOZMA kararı..."
View Full Decision (Turkish)

3. Court of Cassation General Assembly Precedent Decision: Termination at 90%+ Physical Completion

Court of Cassation, General Assembly of Civil Chambers – File: 2024/252, Decision: 2025/310

Summary: Where the physical completion rate of the construction is 90% or above, the landowner's right to terminate the agreement for delay is restricted. In such cases, the court must primarily order the contractor to complete the outstanding works and award compensation for damages caused by the delay.

"...Hukuk Dairesinin 23.02.2023 tarihli ve 2022/4855 Esas, 2023/1071 Karar sayılı BOZMA kararı..."
View Full Decision (Turkish)